College at Geneseo | T000138 |
$15,710.00
|
$1,760.00 |
03/09/2015 | 12/31/2015 | PROJECT NO. M06394 - FLOORING | Contracts Not Subject to OSC Pre-Audit | 03/06/2015 |
College at Geneseo | T000137 |
$15,464.95
|
$4,680.00 |
01/02/2015 | 12/31/2018 | PROJECT #L06361, LAUDERDALE HE | Contracts Not Subject to OSC Pre-Audit | 12/20/2014 |
College at Geneseo | T000193 |
$26,936.26
|
$26,936.26 |
10/01/2019 | 04/01/2021 | REHABILITATE ELEVATOR- MERRITT | Contracts Not Subject to OSC Pre-Audit | 10/03/2019 |
College at Geneseo | T000097 |
$17,022.82
|
$17,022.82 |
11/19/2010 | 12/31/2011 | PROJECT M06348 - REPLACE BALCONY DECK AND RAILING-COLLEGE UNION | Contracts Not Subject to OSC Pre-Audit | 12/10/2010 |
State University Construction Fund | T005449 |
$51,077.25
|
$51,077.25 |
02/02/2009 | 02/01/2014 | INFORMATION TECHNOLOGY INFRASTRUCTURE SUCF 23202 CANTON ATC | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
College at Geneseo | T000230 |
$57,566.96
|
$41,977.52 |
08/19/2021 | 10/01/2023 | REPLACE POOL SCUPPER BOX AND D | Contracts Not Subject to OSC Pre-Audit | 08/23/2021 |
College at Fredonia | T000201 |
$93,135.93
|
$90,359.23 |
07/11/2011 | 08/31/2013 | DESIGN SERVICES TO COMPLETE PROJECT #05324, FIELDHOUSE BLEACHER REPLACEMENT | Contracts Not Subject to OSC Pre-Audit | 08/11/2011 |
College at Brockport | T110635 |
$300,321.00
|
$161,741.78 |
02/03/2012 | 06/30/2013 | DESIGN FOR POOL STABILIZATION | Contracts Not Subject to OSC Pre-Audit | 05/09/2012 |
College at Geneseo | T000227 |
$19,502.82
|
$19,502.82 |
07/21/2021 | 11/01/2023 | HEATING PLANT STACK RENOVATION | Contracts Not Subject to OSC Pre-Audit | 07/21/2021 |