Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
SUNY at Buffalo | T300015 |
$499,999.00
|
$499,999.00 |
03/05/2012 | 10/31/2013 | DESIGN PROJECT 2009-066 COOKE | Contracts Not Subject to OSC Pre-Audit | 05/09/2012 |
SUNY at Stony Brook | T002154 |
$5,996,630.60
|
$4,689,887.95 |
11/02/2018 | 12/31/2023 | I-DIME | Contracts Not Subject to OSC Pre-Audit | 02/14/2019 |
SUNY at Stony Brook | T003270 |
$7,307,611.00
|
$1,248,387.74 |
08/01/2022 | 10/31/2025 | STONY BROOK MULTI-DISCIPLINARY | Contracts Not Subject to OSC Pre-Audit | 01/10/2024 |
State University Construction Fund | T005931 |
$215,828.13
|
$215,828.13 |
03/20/2012 | 03/20/2017 | SUCF 07846 HARPUR SCIENCE PROGRAM STUDY SUNY AT BINGHAMTON | Contracts Not Subject to OSC Pre-Audit | 03/26/2012 |
State University Construction Fund | T006640 |
$4,512,000.00
|
$2,241,589.72 |
06/23/2021 | 06/23/2026 | SUCF221033 Renovate Agricultu | Contracts Not Subject to OSC Pre-Audit | 06/24/2021 |
State University Construction Fund | T005730 |
$3,955,589.79
|
$3,955,589.79 |
10/06/2010 | 05/03/2021 | SUCF 20163 NEW ACADAMIC RESEARCH BUILDING SUNY ESF | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
State University Construction Fund | T006806 |
$6,840,000.00
|
$468,168.78 |
03/16/2023 | 03/16/2028 | SUCF011011 Renovate Building | Contracts Not Subject to OSC Pre-Audit | 03/16/2023 |
State University Construction Fund | T006517 |
$10,279,000.00
|
$4,445,697.46 |
09/06/2019 | 09/06/2024 | SUCF161026 Renovate Plant Sci | Contracts Not Subject to OSC Pre-Audit | 09/10/2019 |
State University Construction Fund | T005960 |
$3,514,732.10
|
$3,514,732.10 |
06/06/2012 | 06/06/2017 | AMENDMENT 4 FOR CONTRACT T0059 | Contracts Not Subject to OSC Pre-Audit | 07/20/2012 |