Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
SUNY at Albany | T004029 |
$240,880.35
|
$232,180.35 |
10/16/2011 | 12/30/2012 | ES-03 & AS-103 LIFE/SAFETY RENOVATIONS - CONSTRUCTION | Contracts Not Subject to OSC Pre-Audit | 10/12/2011 |
SUNY at Albany | D210034 |
$1,187,790.15
|
$1,187,789.81 |
12/11/2021 | 01/31/2024 | ETEC Building breakout construction project #1 Albany County | Construction - Miscellaneous | 12/01/2021 |
SUNY at Albany | T005158 |
$2,322,548.68
|
$2,322,403.68 |
02/02/2016 | 03/02/2018 | ELEVATOR RENOVATIONS - PHASE 3 | Contracts Not Subject to OSC Pre-Audit | 02/23/2016 |
Dormitory Authority of the State of New York | D218522 |
$5,850,000.00
|
$0.00 |
03/22/2022 | 09/27/2024 | PA filed contract Capital District PC inpatient renovations associated asbestos abatement | Contracts Not Subject to OSC Pre-Audit | 06/14/2022 |
Office of General Services - Design & Construction | D44149C |
$166,006.00
|
$166,006.00 |
11/17/2011 | 09/12/2012 | UPGRADE CONCESSION STAND STATE OFFICE BLDG CAMPUS, ALBANY | Construction - Building | 11/17/2011 |
Office of Parks Recreation & Historic Preservation | D004644 |
$3,046,958.00
|
$3,046,958.00 |
05/27/2015 | 04/14/2017 | SA JBT Visitors Center Construction John Boyd Thacher State Park Voorheesville NY (General Const) | Construction - Building | 05/27/2015 |
Office of General Services - Design & Construction | DQ1548C |
$531,300.00
|
$529,204.00 |
05/09/2013 | 11/07/2014 | PROVIDE COLD STORAGE FACILITY - STATE ARMORY TROY NY | Construction - Building | 05/09/2013 |
State University Construction Fund | T006448 |
$1,601,511.00
|
$1,601,511.00 |
07/30/2018 | 08/14/2020 | SUCF011008 Rehab Toilet Rooms | Contracts Not Subject to OSC Pre-Audit | 08/08/2018 |
State University Construction Fund | T006503 |
$3,459,317.00
|
$3,459,317.00 |
06/18/2019 | 02/15/2023 | SUCF011008 Rehab Toilet Rooms | Contracts Not Subject to OSC Pre-Audit | 06/26/2019 |
State University Construction Fund | D006598 |
$2,536,368.00
|
$2,526,368.00 |
01/14/2021 | 12/15/2023 | Renovation of restrooms in campus center, humanities, and social science buildings at SUNY Albany | Construction - Building | 01/08/2021 |
Office of Parks Recreation & Historic Preservation | D004612 |
$197,710.25
|
$197,710.25 |
04/16/2015 | 10/13/2015 | Olana State Historical Site Visitor Center Restroom Restoration Hudson NY | Construction - Building | 04/16/2015 |
Office of General Services - Design & Construction | D45790C |
$747,236.00
|
$745,411.00 |
10/29/2019 | 01/24/2022 | Rehab Restrooms Bldg 1 Capital District Psychiatric Center Albany County | Construction - Building | 10/29/2019 |