Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
SUNY at Buffalo | C001258 |
$2,947,308.00
|
$2,444,376.69 |
04/01/2016 | 03/31/2021 | HVAC/STEAM/MECHANICAL EMERGENCY AND ROUTINE SERVICES | Service - Building Services | 05/11/2016 |
State University Construction Fund | T005543 |
$300,832.00
|
$300,832.00 |
07/15/2009 | 11/15/2011 | HOSCHSTETTER/FILLMORE ACAD CNTRS-RPL AIR HANDLING SUCF 30480 SUNY BUFFALO | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
SUNY at Buffalo | C001277 |
$2,964,142.00
|
$2,215,631.55 |
07/01/2019 | 06/30/2022 | HVAC/Steam/Mechanical Emergency and Routine Services | Service - Building Services | 07/01/2019 |
SUNY at Buffalo | T500157 |
$175,384.53
|
$175,384.53 |
03/02/2022 | 05/01/2024 | 2021-031 UPGRADE CHILLED WATER | Contracts Not Subject to OSC Pre-Audit | 03/21/2022 |
SUNY at Buffalo | D000041 |
$739,575.00
|
$282,264.00 |
06/15/2023 | 08/10/2025 | Slee Hall air handling unit replacement at SUNY Buffalo | Construction - Utilities | 06/15/2023 |
SUNY at Buffalo | T500160 |
$263,011.68
|
$249,861.10 |
03/15/2022 | 06/01/2024 | 2019-179 SQUIRE 1ST FLOOR HVAC | Contracts Not Subject to OSC Pre-Audit | 05/02/2022 |
SUNY at Buffalo | C001329 |
$6,975,852.00
|
$3,526,879.20 |
08/01/2022 | 07/31/2025 | HVAC, steam and mechanical emergency and routine services | Equipment - Other | 09/09/2022 |
College at Buffalo | T180198 |
$25,315.00
|
$25,315.00 |
05/13/2019 | 12/31/2019 | SAMC LABORATORY EXHAUST FAN (L | Contracts Not Subject to OSC Pre-Audit | 05/14/2019 |
College at Buffalo | T180156 |
$9,645.00
|
$9,645.00 |
07/09/2018 | 11/30/2018 | SAMC DAMPER INSTALLATIONS | Contracts Not Subject to OSC Pre-Audit | 07/10/2018 |
College at Buffalo | T140043 |
$1,502,000.00
|
$751,000.00 |
02/06/2015 | 10/01/2015 | REHAB ROCKWELL HALL HVAC SYSTE | Contracts Not Subject to OSC Pre-Audit | 02/07/2015 |
College at Buffalo | T170152 |
$7,314.00
|
$7,314.00 |
05/04/2018 | 09/30/2018 | NEW DUCTLESS SPLIT SYSTEM FOR | Contracts Not Subject to OSC Pre-Audit | 05/05/2018 |
Office of General Services - Design & Construction | DEC276H |
$300,000.00
|
$287,407.00 |
03/19/2013 | 01/31/2014 | REPLACE UNDERGROUND HEAT LINES ORLEANS CORRECTIONAL FACILITY | Construction - Building | 04/26/2013 |
Office of General Services - Design & Construction | DED346P |
$100,000.00
|
$11,412.00 |
11/15/2016 | 05/14/2017 | Investigate/Repair Outside Sewer Valve Buffalo Armory Erie County | Construction - Building | 12/07/2016 |
Office of General Services - Design & Construction | DQ1434H |
$446,577.00
|
$438,816.00 |
02/25/2011 | 01/26/2013 | REPLACE BOILER STACK AND ECONOMIZERS BLDG 22 WENDE CF | Construction - Building | 12/21/2011 |
Office of General Services - Design & Construction | DEC277H |
$300,000.00
|
$292,798.00 |
03/19/2013 | 01/31/2014 | REPLACE LEAKING UNDERGROUND HEAT LINE ORLEANS CORRECTIONAL FACILITY | Construction - Building | 04/25/2013 |
Office of General Services - Design & Construction | DEB978H |
$200,000.00
|
$189,093.00 |
07/06/2012 | 12/27/2013 | REPAIR UNDERGROUND CONDENSATE LINE AND SHUT OFF VALVE NEAR BUILDING 60 COLLINS CF | Construction - Miscellaneous | 08/03/2012 |
Office of General Services - Design & Construction | DEC441H |
$300,000.00
|
$201,226.00 |
09/10/2013 | 11/19/2015 | REPLACE LEAKING UNDERGROUND HEAT LINES ORLEANS CF | Construction - Building | 10/17/2013 |
Office of General Services - Design & Construction | DED419H |
$300,000.00
|
$246,637.00 |
02/09/2017 | 05/18/2018 | Repair air handler units 3&4, Bldg. 132, Attica CF, Wyoming Cnty. | Construction - Miscellaneous | 03/13/2017 |
Office of General Services - Design & Construction | DEC279H |
$300,000.00
|
$294,660.00 |
03/19/2013 | 01/31/2014 | RESTORE UNDERGROUND HEAT HOT WATER LINES ORLEANS CORRECTIONAL FACILITY | Construction - Building | 04/29/2013 |
Office of General Services - Design & Construction | DEC278H |
$300,000.00
|
$298,887.00 |
03/19/2013 | 04/07/2014 | REPLACE LEAKING UNDERGROUND HEAT LINE ORLEANS CORRECTIONAL FACILITY | Construction - Building | 04/25/2013 |
Office of General Services - Design & Construction | D46048H |
$13,997,000.00
|
$9,666,809.83 |
03/28/2022 | 11/16/2024 | Install above ground heating system & replace underground hot water lines Lakeview CF Chautauqua Co | Construction - Building | 03/28/2022 |
Office of General Services - Design & Construction | DEE597H |
$400,000.00
|
$390,786.06 |
07/07/2021 | 07/02/2023 | Repair/replace failed chiller Albion CF Orleans County Region 7 | Construction - Building | 08/17/2021 |
SUNY at Buffalo | T500113 |
$244,901.00
|
$244,901.00 |
05/15/2019 | 03/02/2020 | PROJECT 2018-187 CHEMICAL STOR | Contracts Not Subject to OSC Pre-Audit | 06/07/2019 |