Office of General Services - Design & Construction | DEE963V |
$300,000.00
|
$132,666.77 |
03/15/2023 | 09/11/2024 | Repair switchgear at Bedford Hills Correctional Facility Westchester County | Construction - Building | 04/11/2023 |
Office of General Services - Design & Construction | DED639H |
$125,000.00
|
$52,907.00 |
11/07/2017 | 02/05/2018 | Investigate & Repair Heating Line, Bldg 11, Greene CF, Greene County | Construction - Building | 11/30/2017 |
Office of General Services - Design & Construction | DEB619P |
$100,000.00
|
$99,012.00 |
08/17/2011 | 12/15/2011 | REPAIR LEAKING WATER MAIN ADJACENT TO BLDG #2 BEACON CF | Construction - Building | 10/14/2011 |
Office of General Services - Design & Construction | DEB960G |
$75,000.00
|
$15,294.00 |
06/19/2012 | 10/17/2012 | REPAIR WATER MAIN BREAK @ QWL OTISVILLE CF | Construction - Building | 07/25/2012 |
Office of General Services - Design & Construction | DED739V |
$100,000.00
|
$8,990.00 |
02/06/2018 | 08/05/2018 | Replace Switchgear Batteries, Generator 1 & 2 Blg 102 Manhattan PC NY County | Construction - Building | 03/21/2018 |
Office of General Services - Design & Construction | DED740P |
$300,000.00
|
$279,901.00 |
02/09/2018 | 06/09/2018 | Restore Sanitary Sewer Lines Bldg 103 Manhattan PC New York County | Construction - Building | 03/20/2018 |
Office of General Services - Design & Construction | DEC847B |
$265,000.00
|
$191,747.00 |
02/12/2015 | 06/12/2015 | Filter Fuel & Clean Tanks, Various Buildings, South Beach PC | Construction - Building | 03/09/2015 |
Office of General Services - Design & Construction | DED361B |
$600,000.00
|
$38,060.00 |
11/30/2016 | 06/15/2018 | Remediate Oil Spill St Albans Veterans Home Queens County | Construction - Building | 01/06/2017 |
Office of General Services - Design & Construction | DEC150P |
$75,000.00
|
$10,348.00 |
11/29/2012 | 03/29/2013 | REPAIR FAILED BACK FLOW PREVENTER AND RESTORE WATER SERVICE AT RICHARD C WARD ATC | Construction - Building | 01/08/2013 |
Office of General Services - Design & Construction | DEC533G |
$300,000.00
|
$60,571.00 |
01/08/2014 | 05/08/2014 | REPAIR WATER MAIN BREAK BROOKLYN DDSO | Construction - Building | 02/03/2014 |
Office of General Services - Design & Construction | DEE837P |
$600,000.00
|
$563,552.33 |
06/22/2022 | 04/15/2024 | Repair Foam System Ronkonkoma AASF Suffolk County | Construction - Building | 07/22/2022 |
Office of General Services - Design & Construction | DEA963G |
$300,000.00
|
$206,785.00 |
10/27/2009 | 11/26/2011 | CUT & CAP UTILITIES FOR SAFETY CONSIDERATIONS BERNARD FINESON DDSO | Construction - Building | 04/06/2011 |
Office of General Services - Design & Construction | DEC292H |
$200,000.00
|
$118,388.00 |
03/29/2013 | 07/27/2013 | REPAIR UNDERGROUND STEAM LINE BREAK AT SUNY MARITIME COLLEGE | Construction - Building | 05/24/2013 |
Office of General Services - Design & Construction | DED271C |
$100,000.00
|
$87,367.00 |
08/05/2016 | 02/01/2017 | Repair Deteriorated Structural Membrane-Floor System-Institute of Basic Research-Richmond County | Construction - Building | 08/26/2016 |
Office of General Services - Design & Construction | DEB737H |
$200,000.00
|
$181,649.00 |
10/27/2011 | 08/13/2012 | REPAIR FAILED BOILERS BUILDINGS 50 & 60 BEACON CF | Construction - Building | 02/29/2012 |
Office of General Services - Design & Construction | DEC603G |
$300,000.00
|
$261,983.00 |
03/27/2014 | 07/25/2014 | REPAIR UNDERGROUND STEAM LEAK & SINK HOLE BUILDING 105 MANHATTAN PC | Construction - Building | 04/28/2014 |
Office of General Services - Design & Construction | DEE184P |
$600,000.00
|
$567,811.00 |
10/01/2019 | 03/29/2020 | Repair Steam Pipes Building 103 Floors 6 7 & 8 Manhattan PC New York County | Construction - Building | 11/06/2019 |
Office of General Services - Design & Construction | DED117E |
$480,000.00
|
$476,564.00 |
01/12/2016 | 03/10/2017 | Provide Int. & Ext. Renovation | Contracts Not Subject to OSC Pre-Audit | 02/25/2016 |
Office of General Services - Design & Construction | DED352G |
$101,840.00
|
$101,433.00 |
11/16/2016 | 03/16/2017 | Investigate/Repair Broken Water Main Bldg 103 Kirby Forensic PC | Construction - Building | 12/14/2016 |
Office of General Services - Design & Construction | DED154V |
$200,000.00
|
$11,227.00 |
02/16/2016 | 06/15/2016 | Restore Electrical Service, Bldg 1, Bronx PC | Construction - Building | 03/24/2016 |
Office of General Services - Design & Construction | DED332G |
$75,000.00
|
$18,318.00 |
10/29/2016 | 02/26/2017 | Repair Sewer Main Bldg 58 Rockland PC Rockland County | Construction - Building | 11/18/2016 |
Office of General Services - Design & Construction | DEC015G |
$300,000.00
|
$237,853.00 |
08/24/2012 | 12/22/2012 | CORRECT SINK HOLES BUILDINGS 102 103 105 MANHATTAN PC | Construction - Building | 10/19/2012 |
Office of General Services - Design & Construction | DEC679P |
$300,000.00
|
$16,658.00 |
06/27/2014 | 10/25/2014 | REPAIR REPLACE LEAKING WATER LINES TACONIC CORRECTIONAL FACILITY WESTCHESTER COUNTY | Construction - Building | 08/05/2014 |
Office of General Services - Design & Construction | DEE250P |
$300,000.00
|
$37,239.00 |
12/20/2019 | 04/18/2020 | Replace Failed Sanatary Pumps Pilgrim PC Bldg 100 Suffolk County | Construction - Building | 01/21/2020 |
Office of General Services - Design & Construction | DEE916V |
$300,000.00
|
$69,166.30 |
12/16/2022 | 04/15/2023 | Repair electric feed at Bethpage State Park Nassau County | Construction - Building | 02/08/2023 |
Office of General Services - Design & Construction | DEC801G |
$300,000.00
|
$222,367.00 |
11/29/2014 | 03/31/2015 | REPAIR WATER MAIN BREAK - SUNY MARITIME BRONX NY | Construction - Building | 01/28/2015 |
Office of General Services - Design & Construction | DEE639G |
$1,500,000.00
|
$1,401,057.00 |
09/07/2021 | 05/13/2022 | Provide tree removal & cleanup Caumsett SP Suffolk County Region 1 | Construction - Building | 10/06/2021 |
Office of General Services - Design & Construction | DEE467G |
$150,000.00
|
$48,107.00 |
11/04/2020 | 03/04/2021 | Repair heat supply duct Bldg 2E Downstate CF Dutchess County | Construction - Building | 12/11/2020 |
Office of General Services - Design & Construction | DEC202G |
$300,000.00
|
$206,355.00 |
01/14/2013 | 10/14/2013 | CORRECT WATER LINE BREAK POWER HOUSE BRONX PC | Construction - Building | 03/07/2013 |
Office of General Services - Design & Construction | DEB771P |
$75,000.00
|
$38,279.00 |
11/21/2011 | 03/20/2012 | RESTORE BROKEN WATER MAIN BLDG 54 ROCKLAND PC | Construction - Building | 01/11/2012 |
Office of General Services - Design & Construction | DEB782C |
$300,000.00
|
$246,410.00 |
12/08/2011 | 12/13/2012 | SECURE BLDGS FOR CLOSURE ARTHURKILL CF | Construction - Building | 01/11/2012 |
Office of General Services - Design & Construction | DEC921C |
$200,000.00
|
$39,746.00 |
04/29/2015 | 10/01/2015 | CORRECT WATER INFILTRATION,ELEVATOR SHAFT C, BLDG 2, KINGSBORO PC | Construction - Building | 05/21/2015 |
Office of General Services - Design & Construction | DEC350C |
$300,000.00
|
$261,840.00 |
06/08/2013 | 10/06/2013 | CLEAN UP DAMAGED AREAS & TEMPORARILY COVER ROOF AT CREEDMOOR PC | Construction - Building | 07/17/2013 |
Office of General Services - Design & Construction | DEB860H |
$300,000.00
|
$55,915.00 |
02/28/2012 | 06/27/2012 | RESTORE STEAM LINE BUILDING 2 - 19 TUNNEL KINGSBORO PC | Construction - Building | 06/13/2012 |
Office of General Services - Design & Construction | DED802C |
$100,000.00
|
$48,181.00 |
04/27/2018 | 10/29/2018 | Repair Water Infiltration, Stair Tower Whitestone Armory Queens County | Construction - Building | 06/13/2018 |
Office of General Services - Design & Construction | DED807C |
$600,000.00
|
$595,384.00 |
05/02/2018 | 12/04/2018 | Repair Water Damaged Finishes Bldg 149 Bedford Hill CF Wastchester Co | Construction - Building | 06/11/2018 |
Office of General Services - Design & Construction | DEE102E |
$300,000.00
|
$261,562.00 |
05/15/2019 | 11/11/2019 | Remove Sports Lighting Towers Riverbank State Park New York County | Construction - Building | 07/26/2019 |
Office of General Services - Design & Construction | DEE311C |
$300,000.00
|
$228,420.00 |
03/21/2020 | 07/19/2020 | Space conversion to COVID-19 treatment site Manhattan PC New York County | Construction - Building | 05/22/2020 |
Office of General Services - Design & Construction | DEE574P |
$265,000.00
|
$250,381.00 |
05/19/2021 | 01/04/2022 | Repair DHWH, Building 37/40, NYC Children's Center, Bronx Campus | Construction - Building | 06/23/2021 |
Office of General Services - Design & Construction | DEE491G |
$200,000.00
|
$97,296.00 |
12/09/2020 | 04/08/2021 | Repair water main break - bldg 2 Bernard Fineson DDSO | Construction - Building | 02/11/2021 |
Office of General Services - Design & Construction | DEC831C |
$75,000.00
|
$58,442.00 |
01/21/2015 | 08/12/2015 | Correct Deteriorated Concrete Trench Drain - Cook Chill Production Ctr | Construction - Building | 02/26/2015 |
Office of General Services - Design & Construction | DED989P |
$180,000.00
|
$171,828.00 |
12/11/2018 | 04/10/2019 | Repair Sanitary Sewage Pump Station Bronx PC Building 24 | Construction - Building | 02/28/2019 |
Office of General Services - Design & Construction | DED411H |
$300,000.00
|
$136,856.00 |
01/27/2017 | 03/21/2018 | Repair Steam, Hot Water Lines, Values & Pumps Various Location Sing Sing CF Westcheste County | Construction - Building | 03/06/2017 |
Office of General Services - Design & Construction | DEB260H |
$100,000.00
|
$16,627.00 |
07/08/2010 | 11/05/2010 | REPAIR FAILED AIR CONDITIONING UNITS SING SING CF | Construction - Building | 08/12/2010 |
Office of General Services - Design & Construction | DEC064G |
$100,000.00
|
$38,465.00 |
10/23/2012 | 02/20/2013 | REPAIR WATER MAIN BREAK BUILDING 1 INSTITUTE FOR BASIC RESEARCH | Construction - Building | 12/27/2012 |
Office of General Services - Design & Construction | DEC436C |
$266,025.00
|
$265,146.00 |
09/25/2013 | 01/14/2015 | SAFETY & SECURITY REHAB OBSERVATION CELLS BUILDING 126 BEDFORD HILLS CF | Construction - Building | 10/23/2013 |
Office of General Services - Design & Construction | DED609G |
$200,000.00
|
$44,359.00 |
10/10/2017 | 03/19/2018 | Restore Broken Sewer Main at Bronx PC Bldg. 13 Bronx County | Construction - Building | 11/16/2017 |
Office of General Services - Design & Construction | DEE987V |
$300,000.00
|
$65,470.56 |
04/28/2023 | 08/26/2023 | Restore sump pump Bronx Psychiatric Center Buildings 1 & 2 in Bronx County | Construction - Building | 05/19/2023 |
Office of General Services - Design & Construction | DEE976P |
$100,000.00
|
$3,078.78 |
04/13/2023 | 08/11/2023 | Repair steam leak at Manhattan Psychiatric Center New York County | Construction - Building | 05/22/2023 |
Office of General Services - Design & Construction | DED288C |
$106,379.00
|
$99,379.00 |