Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
SUNY at Binghamton | T300132 |
$115,034.70
|
$113,999.10 |
03/08/2012 | 09/08/2012 | HEALTH SERVICES 1ST FLOOR RENOVATIONS - PLUMBING | Contracts Not Subject to OSC Pre-Audit | 02/17/2012 |
SUNY at Binghamton | T300384 |
$113,224.00
|
$113,224.00 |
05/08/2017 | 08/07/2017 | SODEXO FOOD SERVICE UPGRADES - | Contracts Not Subject to OSC Pre-Audit | 04/27/2017 |
SUNY at Binghamton | T300386 |
$76,363.00
|
$76,363.00 |
04/27/2017 | 07/27/2017 | SODEXO FOOD SERVICE UPGRADES - | Contracts Not Subject to OSC Pre-Audit | 04/14/2017 |
SUNY at Binghamton | T300080 |
$216,253.32
|
$210,340.66 |
05/31/2011 | 07/10/2012 | CHENANGO ROOM RENOVATIONS - PLUMBING AND FIRE SUPPRESSION | Contracts Not Subject to OSC Pre-Audit | 05/11/2011 |
SUNY at Binghamton | T300475 |
$112,807.36
|
$112,807.36 |
03/07/2019 | 12/06/2019 | 123649D SCI 3 FRI & GENETICS L | Contracts Not Subject to OSC Pre-Audit | 02/26/2019 |
Department of Transportation | D263088 |
$157,385.06
|
$157,385.06 |
07/18/2016 | 12/31/2017 | I-81 WHITNEY POINT REST AREA SEWER IMPROVEMENTS HVAC (5 TRADE) BROOME CO | Construction - Building | 07/18/2016 |
Office of Parks Recreation & Historic Preservation | D004128 |
$125,177.00
|
$125,160.19 |
08/25/2011 | 12/24/2012 | BATHHOUSE RECONSTRUCTION PLUMBING CHENANGO VALLEY SP | Construction - Building | 08/25/2011 |
Department of Transportation | D263464 |
$539,553.77
|
$539,553.77 |
05/17/2017 | 11/30/2017 | I-81 Southern Tier Welcome Ctr Renovate Bldg. Kirkwood, Broome County (HVAC) | Construction - Building | 05/17/2017 |
Department of Transportation | D263463 |
$149,143.22
|
$149,143.22 |
05/17/2017 | 11/30/2017 | I-81 Southern Tier Welcome Ctr Renovate Bldg. Kirkwood, Broome County (Plumbing) | Construction - Building | 05/17/2017 |
Department of Transportation | D263027 |
$1,443,941.73
|
$1,443,941.73 |
05/05/2016 | 10/21/2017 | I-81 Gateway Rest Area Sewer Improvements, Plumbing, Town of Kirkwood, Broome County | Construction - Building | 05/05/2016 |
Office of General Services - Design & Construction | DQ1393H |
$305,400.00
|
$304,140.00 |
09/28/2009 | 06/26/2011 | REPLACE BOILERS IN BINGHAMTON ARMORY BINGHAMTON, NEW YORK | Construction - Building | 09/28/2009 |
Office of General Services - Design & Construction | DEB826G |
$150,000.00
|
$24,843.00 |
01/24/2012 | 06/22/2012 | REPAIR FAILED DRAINAGE SUBSTRUCTURE BINGHAMTON ARMORY | Construction - Miscellaneous | 02/17/2012 |
Office of Parks Recreation & Historic Preservation | D004127 |
$30,177.00
|
$28,616.99 |
08/25/2011 | 12/24/2012 | BATHHOUSE RECONSTRUCTION MECHANICAL CHENANGO VALLEY SP | Construction - Building | 08/25/2011 |
Department of Transportation | D263087 |
$614,579.09
|
$614,579.09 |
07/18/2016 | 06/30/2018 | I-81 WHITNEY POINT REST AREA SEWER IMPROVEMENTS PLMB (5 TRADE) BROOME CO | Construction - Building | 07/18/2016 |