Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Department of Transportation | D263999 |
$1,955,365.28
|
$1,955,365.27 |
07/29/2019 | 07/31/2020 | Repair Replace/Abandon Storm Water Catch Basins Along Taconic State Parkway Dutchess County | Construction - Highway | 07/29/2019 |
Department of Transportation | D264967 |
$1,879,068.00
|
$1,036,004.63 |
02/17/2023 | 04/03/2024 | Catch basins rehabilitation Taconic State Parkway various locations Westchester County | Construction - Highway | 02/17/2023 |
Department of Transportation | D263438 |
$3,416,310.21
|
$3,416,310.21 |
08/18/2017 | 11/30/2018 | Storm Water basin repair/replace, var loc, Taconic St. Parkway, Columbia County | Construction - Highway | 08/18/2017 |
Office of General Services - Design & Construction | DQ1707C |
$2,578,300.00
|
$1,769,778.75 |
06/05/2019 | 02/01/2023 | Provide Temporary Kitchen & Replace Floors Bldg 144 Cook Chill Production Center Rockland County | Construction - Building | 06/05/2019 |
Department of Transportation | D265220 |
$2,047,110.00
|
$0.00 |
04/26/2024 | 11/30/2024 | Hazardous tree removal on Palisades Interstate Parkway in Orange and Rockland Counties | Construction - Highway | 04/26/2024 |
Office of General Services - Design & Construction | DQ1803C |
$839,700.00
|
$0.00 |
05/19/2021 | 01/25/2023 | Rehabilitate tank containment infrastructure Woodbourne CF Sullivan County | Construction - Building | 05/19/2021 |
Department of Transportation | D262605 |
$3,948,730.53
|
$3,948,730.53 |
10/24/2014 | 08/28/2016 | Paving & Upgrades to existing Pasisades Trailway including new pedestrian bridge, Orangetown | Construction - Highway | 10/24/2014 |