SUNY at Albany | D0A0744 |
$1,402,637.00
|
$1,392,637.00 |
05/22/2006 | 07/10/2007 | REPLACEMENT OF PRIMARY FEEDER-UPTO WN | Construction - Building | 05/18/2007 |
Office of Parks Recreation & Historic Preservation | D006143 |
$6,179,820.00
|
$83,600.00 |
12/15/2023 | 12/14/2025 | Rehabilitation of primary electric system at Saratoga Spa State Park Saratoga County | Construction - Building | 12/15/2023 |
SUNY at Albany | T190155 |
$1,919,650.00
|
$1,919,650.00 |
11/05/2019 | 12/31/2021 | ARC FLASH CONSTRUCTION SERVICE | Contracts Not Subject to OSC Pre-Audit | 01/07/2020 |
SUNY at Albany | D230065 |
$1,824,147.00
|
$282,625.00 |
12/04/2023 | 11/29/2024 | ARC fault remediation at SUNY Albany | Construction - Miscellaneous | 12/07/2023 |
SUNY at Albany | D210090 |
$1,042,682.00
|
$1,037,052.01 |
05/15/2022 | 09/22/2023 | Replacement of building electrical system and asbestos abatement | Construction - Miscellaneous | 05/11/2022 |
College at Geneseo | T000185 |
$31,876.00
|
$31,876.00 |
04/02/2019 | 12/31/2019 | MAIN RELAY REPLACEMENTS- CLARK | Contracts Not Subject to OSC Pre-Audit | 04/04/2019 |
Office of General Services - Design & Construction | DEE529E |
$100,000.00
|
$89,392.00 |
02/09/2021 | 07/07/2021 | Repair hot water heat pumps Bldg 55 Mohawk Correctional Facility Oneida County | Construction - Building | 04/26/2021 |
Office of General Services - Design & Construction | DM2895E |
$598,632.00
|
$598,632.00 |
01/26/2011 | 12/31/2011 | REPAIR TWO GENERATORS GREENE CF | Construction - Building | 11/16/2011 |
Office of General Services - Design & Construction | DEC497E |
$300,000.00
|
$156,195.00 |
11/21/2013 | 11/05/2014 | REPLACE TWO EMERGENCY GENERATOR RADIATORS BUILDING 108 WYOMING CF | Construction - Building | 12/13/2013 |
Office of General Services - Design & Construction | DEB765E |
$100,000.00
|
$8,938.00 |
11/09/2011 | 03/08/2012 | INVESTIGATE & REPAIR POWERLINE & POLE AT ARTHUR RD CAMP SMITH | Construction - Building | 12/13/2011 |
Office of General Services - Design & Construction | D42673E |
$5,252,206.00
|
$5,181,609.00 |
08/04/2015 | 02/24/2019 | Rehabilitate Electrical Distribution System, Electrical, Coxsackie CF | Construction - Building | 08/04/2015 |
Office of General Services - Design & Construction | DEB783E |
$300,000.00
|
$44,227.00 |
12/08/2011 | 12/28/2012 | DECOMMISSION ELECTRICAL SYSTEM (E TRADE) ARTHUR KILL CF | Construction - Building | 01/10/2012 |
Office of General Services - Design & Construction | D45686E |
$554,309.00
|
$554,287.00 |
11/12/2019 | 12/30/2020 | Replace Generator Buildings 8 8A & 9 SOB Albany County | Construction - Building | 11/12/2019 |
Office of General Services - Design & Construction | DEE531E |
$300,000.00
|
$76,956.00 |
02/09/2021 | 06/09/2021 | Repair electric feeder cook chill production center Orangeburg Rockland county | Construction - Building | 04/23/2021 |
Office of General Services - Design & Construction | DEC975E |
$75,000.00
|
$1,657.00 |
07/21/2015 | 11/18/2015 | Investigate & Repair Emergency Generator to Restore Power, South Beach PC | Construction - Building | 08/19/2015 |
Office of General Services - Design & Construction | DEC378E |
$150,000.00
|
$62,344.00 |
07/03/2013 | 12/17/2013 | REPLACE FAILED TRANSFORMER BUILDING 39 NATHAN KLINE RESEARCH INSTITUTE ROCKLAND COUNTY | Construction - Building | 08/02/2013 |
Office of General Services - Design & Construction | D44664E |
$788,300.00
|
$732,300.00 |
02/02/2015 | 07/03/2016 | Electrical Work - Replace Electrical Switches - Empire State Plaza Albany NY | Construction - Building | 02/02/2015 |
Office of General Services - Design & Construction | DEE787E |
$300,000.00
|
$47,155.58 |
03/06/2022 | 07/04/2022 | Repair perimeter electrical system Collins CF Erie County | Construction - Building | 04/13/2022 |
Office of General Services - Design & Construction | DEE274E |
$200,000.00
|
$176,977.00 |
01/23/2020 | 12/30/2020 | Replace Failed Transformer Bronx PC Bronx County | Construction - Building | 02/14/2020 |
Office of General Services - Design & Construction | DEB313E |
$300,000.00
|
$281,154.00 |
08/30/2010 | 06/22/2011 | REPAIR FIRE DAMAGED COOLING TOWER EQUIPMENT SUNY PURCHASE | Construction - Building | 01/05/2011 |
Office of General Services - Design & Construction | DEB317E |
$275,000.00
|
$212,360.00 |
09/13/2010 | 11/30/2011 | REPAIR/ REPLACE FAILING UV LIGHT SYSTEM GREEN HAVEN CF | Construction - Building | 03/15/2012 |
Office of General Services - Design & Construction | DED335E |
$500,000.00
|
$343,663.00 |
11/03/2016 | 06/16/2017 | repair catwalk & electrical deficiencies, Sing Sing CF | Construction - Miscellaneous | 11/22/2016 |
Office of General Services - Design & Construction | D43645E |
$97,300.00
|
$95,500.00 |
03/28/2011 | 11/28/2011 | PROVIDE ELECTRIC FOR TOWERS BIG YARD COXSACKIE CF | Construction - Building | 03/28/2011 |
Office of General Services - Design & Construction | DEC078E |
$2,885,000.00
|
$2,879,367.00 |
10/31/2012 | 08/31/2014 | RESTORE ELECTRIC SERVICE CAMPUS WIDE SOUTHBEACH PC | Construction - Building | 12/04/2012 |
Office of General Services - Design & Construction | DEF125E |
$300,000.00
|
$112,281.58 |
01/05/2024 | 07/03/2024 | Repair perimeter lighting at the Industry Campus in Monroe County | Construction - Building | 02/05/2024 |
Office of General Services - Design & Construction | DEC556E |
$50,000.00
|
$3,313.00 |
02/06/2014 | 08/05/2014 | REPAIR MALFUNCTIONING SITE WIDE GENERATORS AT MOHAWK CF | Construction - Building | 03/20/2014 |
Office of General Services - Design & Construction | DEC561E |
$200,000.00
|
$182,035.00 |
02/14/2014 | 06/30/2014 | REPLACE FAILED BATTERIES AND EXISTING CBU SYSTEM UPSTATE CF | Construction - Building | 03/20/2014 |
Office of General Services - Design & Construction | DEC564E |
$200,000.00
|
$35,012.00 |
02/18/2014 | 06/18/2014 | INVESTIGATE & REPAIR FAILED ELECTRICAL FEEDER BRONX PC | Construction - Building | 03/26/2014 |
Office of General Services - Design & Construction | DEC638E |
$300,000.00
|
$60,432.00 |
05/13/2014 | 11/13/2014 | INVESTIGATE POWER OUTAGE & RESTORE POWER & DAMAGED EQUIPMENT MARCY CF ONEIDA COUNTY | Construction - Building | 06/16/2014 |
Office of General Services - Design & Construction | DEE514E |
$360,000.00
|
$313,376.00 |
01/06/2021 | 05/06/2021 | Repair parking lot light feeder Creedmoor PC bldg 40 Queens County | Construction - Building | 02/17/2021 |
Office of General Services - Design & Construction | DEB468E |
$300,000.00
|
$50,660.00 |
01/27/2011 | 07/26/2011 | RESTORE POWER TO BUILDINGS GENESEO SUC | Construction - Building | 03/08/2011 |
Office of General Services - Design & Construction | DEB485E |
$37,400.00
|
$30,318.00 |
02/17/2011 | 06/17/2011 | REPAIR ELECTICAL DEFICIENCIES HEATING PLANT SING SING CF | Construction - Building | 03/28/2011 |
Office of General Services - Design & Construction | DEE272E |
$300,000.00
|
$216,808.00 |
01/19/2020 | 05/18/2020 | Restore Parking Lot Lights Riverview CF St.Lawrence County | Construction - Building | 02/18/2020 |
Office of General Services - Design & Construction | DEE166E |
$75,000.00
|
$69,743.00 |
08/19/2019 | 12/17/2019 | Investigate & Repair Electrical Issues Bldg 22 State Office Bldg Campus Albany County | Construction - Building | 10/02/2019 |
Office of General Services - Design & Construction | DEE162E |
$240,000.00
|
$232,612.00 |
08/07/2019 | 12/10/2019 | Restore Power Willard Drug Treatment Center Willard Seneca County | Construction - Building | 10/11/2019 |
Office of General Services - Design & Construction | DEB089E |
$75,000.00
|
$26,628.00 |
01/26/2010 | 05/09/2011 | REPAIR FAILED CONTROLS WATER FILTRATION PLANT GREAT MEADOW CF | Construction - Building | 12/01/2010 |
Office of General Services - Design & Construction | D44991E |
$7,012,567.00
|
$2,114,660.13 |
08/12/2022 | 03/19/2025 | Provide generator building Shawangunk CF Ulster County | Construction - Building | 08/12/2022 |
Office of General Services - Design & Construction | D46118E |
$129,208.00
|
$127,632.00 |
06/24/2022 | 12/31/2023 | Provide salt storage bldg DOT Region 8 Electrical Columbia County | Construction - Building | 06/24/2022 |
Office of General Services - Design & Construction | DEE967E |
$100,000.00
|
$38,754.58 |
03/29/2023 | 09/25/2023 | Repair electrical system at Lakeside Beach State Park Monroe County | Construction - Building | 04/11/2023 |
Office of General Services - Design & Construction | DED176E |
$300,000.00
|
$199,255.00 |
04/01/2016 | 07/28/2017 | Repair / Replace Basement Electric Vault Room, Complex 4, Downstate CF | Construction - Building | 04/27/2016 |
Office of General Services - Design & Construction | D44724E |
$755,341.00
|
$755,232.00 |
03/20/2015 | 06/16/2018 | REPLACE POWERHOUSE EMERGENCY GENERATOR, WOODBOURNE CF | Construction - Building | 03/20/2015 |
Office of General Services - Design & Construction | DEE744E |
$150,000.00
|
$57,814.26 |
01/04/2022 | 05/04/2022 | Repair lift station pump Farm at Coxsackie CF Greene County | Construction - Building | 01/31/2022 |
Office of General Services - Design & Construction | DEC759E |
$200,000.00
|
$12,581.00 |
10/22/2014 | 04/20/2015 | REPAIR LEAKING STEAMLINE & DAMAGED ELECTRICAL EQUIPMENT BUILDINGS 2 & 3 COLLINS CF | Construction - Building | 11/17/2014 |
Office of General Services - Design & Construction | DEE813E |
$300,000.00
|
$4,279.97 |
04/18/2022 | 10/14/2022 | Repair elevators buildings. 8,9,11 Upstate CF Franklin County Region 5 | Construction - Building | 05/26/2022 |
Office of General Services - Design & Construction | DED151E |
$300,000.00
|
$144,246.00 |
02/15/2016 | 07/14/2016 | Investigate & Restore Electrical Power, Veterans Nursing Home, Oxford, NY | Construction - Building | 03/14/2016 |
Office of General Services - Design & Construction | DEF059E |
$300,000.00
|
$33,145.97 |
08/30/2023 | 12/28/2023 | Repair security light pole at Eastern Correctional Facility in Ulster County | Construction - Building | 09/21/2023 |
Office of General Services - Design & Construction | D44992E |
$3,557,621.00
|
$3,291,153.96 |
09/03/2020 | 05/14/2024 | Replace High Voltage Switchgear & Generator Ottisville CF Ottisville Orange County | Construction - Building | 09/03/2020 |
Office of General Services - Design & Construction | DEF012E |
$450,000.00
|
$296,810.48 |
06/28/2023 | 07/02/2024 | Repair dairy building foundation wall and duct banks at NYS Fairgrounds in Onondaga County | Construction - Building | 07/27/2023 |
Office of General Services - Design & Construction | D45687E |
$209,049.00
|
$201,369.00 |
11/09/2018 | 03/24/2020 | Provide Chilled Water & Steam Condensate Piping Manhole 12 to 7A SOB Campus Albany County | Construction - Building | 11/09/2018 |
Office of General Services - Design & Construction | DEE923E |
$300,000.00
|
$244,271.53 |
12/26/2022 | 06/24/2023 | Investigate & repair electric Building 74 Alfred State University Allegany County | Construction - Building | 01/25/2023 |