Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Department of Transportation | TR37177 |
$11,384.87
|
$11,384.87 |
02/01/2016 | 12/31/2022 | BIN 1024120 SR 38 OVER BERKSHI | Contracts Not Subject to OSC Pre-Audit | 10/28/2016 |
Department of Transportation | DR34315 |
$1,206,270.00
|
$1,189,457.18 |
06/01/2012 | 12/31/2014 | Track and Bridge Rehabilitation along Owego and Hartford Railway MP288.5 and MP314.7 | Grant | 07/31/2012 |
Department of Transportation | D032928 |
$188,503.47
|
$188,503.47 |
01/20/2011 | 12/31/2015 | GRADE CROSSING IMPROVMENTS AT WHIG STREET NEWARK, TIOGA COUNTY | Construction - Highway | 04/04/2011 |
Department of Transportation | D032926 |
$99,788.13
|
$99,788.13 |
01/20/2011 | 12/31/2015 | REUSE MAST & MOTOR FOR CIRCUITRY TANNERY RD XING NEWARK VALLEY, TIOGA COUNTY | Construction - Highway | 03/30/2011 |
Department of Transportation | D032927 |
$93,262.68
|
$93,262.68 |
01/20/2011 | 12/31/2015 | REUSE MAST & MOTOR C CIRCUITRY WEST CREEK RD XING TIOGA CO | Construction - Highway | 03/31/2011 |
Department of Transportation | DR37586 |
$178,973.35
|
$178,973.35 |
02/15/2019 | 11/18/2021 | Railroad Safety Improvement Grade Crossing Owego & Harford Railway Newark Tioga County | Construction - Highway | 04/29/2019 |
Department of Transportation | DR37587 |
$177,181.00
|
$177,181.00 |
05/15/2017 | 09/21/2021 | Install Lights & Gates Blodgett Road Crossing Newark Tioga County | Construction - Highway | 05/02/2019 |
Department of Transportation | D021644 |
$303,185.95
|
$303,185.95 |
03/02/2004 | 12/31/2010 | CONSTRUCT RUN-AROUND TRACK GATE & CROSSING SIGNAL HARTFORD, CORTLAND COUNTY | Construction - Highway | 05/12/2004 |
Department of Transportation | DR37296 |
$107,201.00
|
$107,201.00 |
04/07/2017 | 10/17/2022 | REIMBURSEMENT AGREEMENT FOR IMPROVEMENT OF STATE ROUTE 38 CROSSING TOWN OF BERKSHIRE TIOGA COUNTY | Construction - Highway | 06/02/2017 |
Department of Transportation | DR37416 |
$0.00
|
$0.00 |
08/29/2017 | 12/03/2020 | PASSENGER & RAIL ASSISTANCE PROGRAM | Grant | 01/16/2018 |
Department of Transportation | D032924 |
$97,269.16
|
$97,269.16 |
01/20/2011 | 12/31/2015 | INSTALL FLASHERS/GATES AT RICHARD RD CROSSING RICHFORD, TIOGA COUNTY | Construction - Highway | 03/30/2011 |
Department of Transportation | D032925 |
$102,126.27
|
$102,126.27 |
01/20/2011 | 12/31/2015 | INSTALL FLASHER AND GATES TANNERY RD CROSSING BERSHIRE, TIOGA COUNTY | Construction - Highway | 03/28/2011 |
Department of Transportation | TR38761 |
$8,667.75
|
$0.00 |
08/02/2019 | 12/31/2025 | AGREEMENT TO PROGRESS SAFETY I | Contracts Not Subject to OSC Pre-Audit | 03/11/2021 |
Department of Transportation | D029758 |
$275,000.00
|
$212,608.57 |
01/17/2008 | 12/31/2015 | RAILROAD FACILITIY CHANGES FOR BRIDGE REPLACEMENT TIOGA COUNTY | Construction - Highway | 07/15/2008 |
Department of Transportation | D029993 |
$1,500,000.00
|
$1,499,902.31 |
02/01/2010 | 12/31/2012 | GOVERNORS 100 MILLION 5 YEAR RAIL PLAN | Grant | 03/16/2010 |
Department of Transportation | D032929 |
$93,788.50
|
$93,788.50 |
01/20/2011 | 12/31/2015 | GRADE IMPROVEMENTS AT PARK SETTLEMENT RD CROSSING OWEGO, TIOGA COUNTY | Construction - Highway | 04/04/2011 |