Vendor Name: VILLAGER CONSTRUCTION INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D264303
Current Contract Amount: $9,072,360.10
Spending to Date: $9,072,360.10
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $9,724,000.00 |
12/24/2020 | 12/31/2021 | Asphalt concrete resurfacing & preventive maintenance I-490 Brighton Pittsford Perinton Monroe Co | 12/24/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $36,031.94 |
CO#2 additional items | 06/17/2021 | |
Amendment | $133,072.89 |
CO # 4 Funding for additional traffic designs signals drainage and new pond items | 11/16/2021 | |
Amendment | $0.00 |
07/31/2022 | CO #07 No cost time extension | 01/07/2022 |
Amendment | $3,070.47 |
CO#8 7 new items for riser assembly & revised pavement repairs & cable & wire item for light poles | 04/11/2022 | |
Amendment | $0.00 |
10/31/2022 | CO#10 No cost time extension | 08/04/2022 |
Amendment | $81.72 |
CO #9 Item in creases and decreases. | 09/14/2022 | |
Amendment | $0.00 |
11/30/2022 | CO #11 No cost time extension | 11/16/2022 |
Amendment | $83,984.92 |
CO #13 new items and item increases | 03/23/2023 | |
Amendment | ($907,881.84) |
CO #12 Clean up | 07/10/2023 |