Vendor Name: BETTE & CRING LLC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D264350
Current Contract Amount: $13,312,688.82
Spending to Date: $13,312,688.82
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $11,845,225.00 |
12/11/2020 | 05/26/2022 | Replacement Route 8 Bridge over Routes 5 & 12 Utica & Hartford Oneida County | 12/11/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $493,315.71 |
CO#1 Guide railing & traffic control | 07/06/2021 | |
Amendment | $146,310.30 |
CO#3 Increases & new force account items | 11/05/2021 | |
Amendment | $0.00 |
09/27/2022 | CO#4 no cost time extension | 02/02/2022 |
Amendment | $231,859.11 |
CO#5 New item bridge repairs | 02/08/2022 | |
Amendment | $37,511.86 |
CO #9 new items construction barricade & temporary positive barrier | 07/15/2022 | |
Amendment | $120,239.82 |
CO#7 New traffic control work items | 07/29/2022 | |
Amendment | $58,919.90 |
CO#10 Increases | 08/23/2022 | |
Amendment | $509,222.45 |
CO#11 Fuel & asphalt price adjustments | 09/08/2022 | |
Amendment | $58,187.98 |
CO#12 new traffic control & micropile install FAW and new guide railing & junction box items | 09/27/2022 | |
Amendment | $0.00 |
11/09/2022 | CO#13 No cost time extension | 10/12/2022 |
Amendment | $0.00 |
11/23/2022 | CO #16 No cost time extension | 11/15/2022 |
Amendment | $46,687.32 |
CO #15 increase item quantities and minor items | 12/01/2022 | |
Amendment | $123,098.83 |
CO#17 field conditions | 12/20/2022 | |
Amendment | $28,339.22 |
CO#18 adds new pull box elevation alteration work & item increases & asphalt price adjustment | 01/13/2023 | |
Amendment | $24,367.59 |
CO#19 place & consolidate concrete in front of the median barriers on both sides of the Rt 8 bridge | 02/06/2023 | |
Amendment | $53,732.85 |
CO#20 item increases for protective sealing & shoulder backup material & cleaning structures | 02/28/2023 | |
Amendment | $7,265.12 |
CO#21 New Items | 03/10/2023 | |
Amendment | $4,946.06 |
CO #22 new earthwork items | 04/06/2023 | |
Amendment | $87,126.17 |
CO #23 Steel price adjustment | 04/27/2023 | |
Amendment | $23,670.27 |
CO#24 Increases in new earthwork and guardrail repair | 05/31/2023 | |
Amendment | $238,360.88 |
CO #26 New items for straight tack coat & cast in place concrete piles | 06/14/2023 | |
Amendment | ($825,697.62) |
CO #27 Increases and decreases | 08/03/2023 |