Vendor Name: FAHS CONSTRUCTION GROUP INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006593
Current Contract Amount: $98,298,197.00
Spending to Date: $96,255,845.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $95,295,000.00 |
09/28/2020 | 03/20/2023 | Health and Wellness Center construction at SUNY Upstate | 09/28/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
12/22/2023 | Term correction | 10/16/2020 |
Amendment | $1,674.00 |
Change order #1 update project sign | 10/22/2021 | |
Amendment | $565,435.00 |
Change order #2 & #3 add pneumatic tube system and dock lights | 11/15/2021 | |
Amendment | $147,144.00 |
Change order #5 surge protective device | 12/15/2021 | |
Amendment | $81,144.00 |
Change order #4 provide additional punched window and louver support | 01/27/2022 | |
Amendment | $150,213.00 |
Change order #6 electrical ductbank changes | 02/11/2022 | |
Amendment | $145,237.00 |
CO#7 & 8 duct work and fiber cable and blocking and power and data revisions | 03/04/2022 | |
Amendment | ($3,551.00) |
Deletion of duct sleeves | 04/07/2022 | |
Amendment | ($81,159.00) |
Change order #11 deduction of window washing system and changes to cooling tower support steel | 04/14/2022 | |
Amendment | $120,156.00 |
Change order #10 incorporate city water requirements | 04/22/2022 | |
Amendment | $7,280.00 |
Change order 12 to provide dimension changes in 6A24 med compressor and vac room | 04/29/2022 | |
Amendment | $19,335.00 |
Change order #13 for dental suite modifications | 05/02/2022 | |
Amendment | ($1,994.00) |
Change order 14 to eliminate elevator mesh screen | 05/03/2022 | |
Amendment | $109,068.00 |
Change order #15 secondary sealant joint at windows | 05/12/2022 | |
Amendment | ($2,288.00) |
Change order #16 credit for reduction in piping, fittings valves and related labor | 06/10/2022 | |
Amendment | ($7,981.00) |
Change order #'s 17 and 18- add key cores at doors, modify pediatric privacy curtains | 08/22/2022 | |
Amendment | $52,708.00 |
Change order #19- modify electronic access control and security in wall infrastructure | 09/02/2022 | |
Amendment | $68,592.00 |
Change orders #20 and 21 for waste storage room reconfiguration and additional ductwork | 10/27/2022 | |
Amendment | $68,953.00 |
Change order #22 is to modify information technology and data cable systems | 11/29/2022 | |
Amendment | ($7,377.00) |
Change order #23 is a deductive to modify site concrete seat wall, trench drains, and grading | 12/02/2022 | |
Amendment | ($3,490.00) |
Change order #24 is a credit for change in door hinges | 01/19/2023 | |
Amendment | $139,005.00 |
Change order #25 is to add mechanical, electrical, and structural work at the radiology suite | 02/03/2023 | |
Amendment | $24,939.00 |
Change order #26 is to provide electrical and HVAC support for pneumatic tube system | 02/09/2023 | |
Amendment | $39,206.00 |
Change order #27 provide power and data for pneumatic tube transfer and tube stations | 02/10/2023 | |
Amendment | $375,627.00 |
Change order #28, #29 and #30 are for various changes | 04/13/2023 | |
Amendment | $4,259.00 |
Change order #31 is to provide cafe flooring, mural credit, and a new platform | 04/17/2023 | |
Amendment | $187,649.00 |
Change order #32 is to provide MRI equipment provisions | 05/08/2023 | |
Amendment | $98,233.00 |
Change order #33 for reconfiguration of lockers | 05/26/2023 | |
Amendment | $12,327.00 |
Change order 34 for power to exterior valet kiosk | 08/11/2023 | |
Amendment | $217,798.00 |
Change order 35 is to provide imaging suite humidification provisions | 08/30/2023 | |
Amendment | $12,467.00 |
Change order 36 for modification of cooling capacity in medication storage rooms | 12/13/2023 | |
Amendment | $0.00 |
08/30/2024 | Extension in date due to guarantee period findings | 01/17/2024 |
Amendment | $462,588.00 |
Change order 37 to modify cooling capacity at medication rooms | 01/24/2024 |