Vendor Name: FAHS CONSTRUCTION GROUP INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006566
Current Contract Amount: $13,756,161.00
Spending to Date: $13,674,035.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $13,398,000.00 |
08/19/2020 | 01/02/2023 | Phase 2 renovations to the Science IV building at Binghamton University | 08/19/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $18,999.00 |
Change order for removal of existing furniture per campus request | 11/10/2020 | |
Amendment | $9,671.00 |
Change order for addition of automatic door operators on restrooms per campus request | 12/15/2020 | |
Amendment | $1,169.00 |
Change order for hardware upgrades to control door access per campus request | 12/17/2020 | |
Amendment | $23,158.00 |
Increase contract amount | 01/08/2021 | |
Amendment | $6,605.00 |
Change order #6 office shelving | 05/21/2021 | |
Amendment | $438.00 |
Change order #7 relocate the blue light and telephone to the Vestibule entrance | 08/03/2021 | |
Amendment | $24,690.00 |
Change order #8 provide corridor IT cable pathway on the Ground, 1st, 2nd and 3rd floors | 09/15/2021 | |
Amendment | ($250,000.00) |
Reduction of the contract field order allowance | 01/21/2022 | |
Amendment | $121,774.00 |
Change orders #9 and 11-12 to replace flooring bases, remove tank and add electrical infrastructure | 01/27/2022 | |
Amendment | $16,802.00 |
Change order #s 13, 14 and 15- various additions/deletions | 08/29/2022 | |
Amendment | $1,552.00 |
Change orders #14 and #15- budget modification | 08/29/2022 | |
Amendment | $29,575.00 |
Change order #16 - new controls for fans, compressor modifications, pipe support and electrical work | 09/09/2022 | |
Amendment | $92,380.00 |
Change orders #17, #18 and #19 for various changes | 10/07/2022 | |
Amendment | $713.00 |
Change order #20 provide additional power for card access | 10/21/2022 | |
Amendment | $14,155.00 |
Change order #21 to revise corridor linear diffuser locations | 11/08/2022 | |
Amendment | $19,403.00 |
Change order 22 and 23 for relocation of a number of items | 12/23/2022 | |
Amendment | $38,870.00 |
Change order #24 is a credit and #25 is to revise heat exchange piping and master gas shutoff | 02/14/2023 | |
Amendment | $56,517.00 |
Change orders 26 and 27 are to relocate controlled temperature room and duct sealing and painting | 03/02/2023 | |
Amendment | $0.00 |
04/30/2024 | Administrative term adjustment | 06/13/2023 |
Amendment | $15,609.00 |
Change order 28 revise compressor power | 06/29/2023 | |
Amendment | $16,259.00 |
Change order 29 additional funding to cover necessary overtime hours | 07/27/2023 | |
Amendment | $6,086.00 |
Change order 30 for floor tile replacement | 10/27/2023 | |
Amendment | $93,736.00 |
Change order 31 for replacement of electrical panels and breakers | 12/13/2023 |