Vendor Name: LANCASTER DEVELOPMENT & TULLY CONSTRUCTION CO LLC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D264101
Current Contract Amount: $48,467,434.92
Spending to Date: $48,467,434.92
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $45,569,896.38 |
06/17/2020 | 11/30/2022 | Bridge Highway & Culvert Rehab & Construction I 88 Otsego & Schoharie Counties | 06/18/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($80,160.00) |
CO#1 New Items and decreases. | 09/14/2020 | |
Amendment | ($120,000.00) |
CO#2 Document Change Milestone Date Change & Decrease Item Document Control Management Eliminated | 09/29/2020 | |
Amendment | $112,769.32 |
Change order #3 new Items pavement symbols & asphalt | 01/29/2021 | |
Amendment | $95,000.00 |
Change order #5 new item full depth roadway repairs | 06/01/2021 | |
Amendment | $136,788.57 |
CO # 7 Additional repairs and railings | 09/17/2021 | |
Amendment | $1,318,469.55 |
CO#9 Item increases and new item | 12/02/2021 | |
Amendment | $23,331.03 |
CO#12 New items for rail reset & proprietary portion of end assembly upgrade | 01/20/2022 | |
Amendment | $115,674.16 |
CO#14 increase & add items | 02/15/2022 | |
Amendment | $316,655.45 |
CO#15 new guide rail end assembly reset work items | 04/27/2022 | |
Amendment | $3,250,000.00 |
CO#19 Asphalt & fuel adjustment increases | 07/18/2022 | |
Amendment | $3,180.19 |
CO#21 traffic control item increase | 09/06/2022 | |
Amendment | $190,810.94 |
CO#16 New sign items | 09/19/2022 | |
Amendment | $20.50 |
CO#25 New items compost substitution | 11/03/2022 | |
Amendment | $117,831.32 |
CO# 23 New items polymer overlay | 11/21/2022 | |
Amendment | $52,968.76 |
CO#24 New item | 12/28/2022 | |
Amendment | $0.00 |
12/31/2022 | CO#30 time extension | 01/23/2023 |
Amendment | $15,114.76 |
CO#27 full depth repairs | 02/15/2023 | |
Amendment | $56,300.16 |
CO#28 Additional work | 03/08/2023 | |
Amendment | $338,300.00 |
CO#31 Repair work on various bridge decks | 03/14/2023 | |
Amendment | $3,632.72 |
CO#32 new items for repairing guiderail from accidents & crossovers removed & median restored | 04/05/2023 | |
Amendment | ($332,752.39) |
CO #34 New items | 06/28/2023 | |
Amendment | ($2,716,396.50) |
CO#35 Cleanup & guiderail repairs | 02/01/2024 |