Vendor Name: HARRISON & BURROWES BRIDGE CONSTRUCTORS INC
Authority Name: Thruway Authority
Department/Facility Name: New York State Thruway Authority
Contract Number: D214742
Current Contract Amount: $14,508,014.62
Spending to Date: $0.00
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $15,872,158.72 |
02/28/2020 | 11/19/2021 | Replacement of I 87 bridge over route 207 Orange County | 02/28/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($7.06) |
Change order #1 credit to the State | 06/11/2021 | |
Amendment | ($5.82) |
CO #2 Item in creases and decreases for reconciliation | 12/20/2021 | |
Amendment | $0.00 |
06/01/2022 | CO#2 No cost time extension | 01/20/2022 |
Amendment | $0.00 |
07/31/2022 | No cost time extension | 06/17/2022 |
Amendment | $0.00 |
09/30/2022 | No cost time extension | 08/02/2022 |
Amendment | ($168,037.50) |
CO#3 New items guide railing | 09/09/2022 | |
Amendment | ($926,899.11) |
CO#4 item increases & decreases excavation topsoil & hot mix asphalt | 09/08/2022 | |
Amendment | ($269,109.04) |
CO #5 for removal of two items and addition of two items | 11/21/2022 | |
Amendment | ($85.57) |
CO 6 SA1F Final agreement | 01/10/2023 |