Vendor Name: HARRISON & BURROWES BRIDGE CONSTRUCTORS INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D264093
Current Contract Amount: $22,445,360.64
Spending to Date: $22,445,360.64
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $23,643,236.43 |
02/27/2020 | 09/30/2021 | Bridge replacement & intersection realignment Rt 28 over Esopus Creek Town Shandaken Ulster County | 02/27/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $61,635.12 |
CO#4 New Item for Robotic Total Station& Survey Field Controller | 08/12/2020 | |
Amendment | $3,519.05 |
CO# 1 New work item | 10/22/2020 | |
Amendment | ($28,906.60) |
CO#7 Increased and decreased quantities in culvert items | 12/21/2020 | |
Amendment | $11,580.87 |
Change order #10 structure pile overruns | 02/10/2021 | |
Amendment | $8,667.71 |
Change order #13 new incidental construction | 06/10/2021 | |
Amendment | $0.00 |
11/30/2021 | Change order #14 no cost time extension | 09/08/2021 |
Amendment | $3,025.96 |
CO#17 Additional work to address field changes | 12/13/2021 | |
Amendment | $0.00 |
12/31/2021 | CO#19 No cost time extension | 12/21/2021 |
Amendment | $968,328.57 |
CO#20 Item increases and new items intersection shift | 04/15/2022 | |
Amendment | ($2,225,726.47) |
CO #21 Increases & decreases in supplies - clean up change order | 07/03/2023 |