Vendor Name: J & N CONSTRUCTION GROUP CORP
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D44798C
Current Contract Amount: $33,175,348.00
Spending to Date: $27,894,930.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $28,850,000.00 |
08/09/2019 | 08/21/2022 | Repair Exterior Facade Windows & Roof Shirley Chisholm State Office Building Kings County | 08/09/2019 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
10/30/2022 | Change order #2 control #75290 no cost time extension | 02/01/2021 |
Amendment | $488,513.00 |
CO#1 75306 Provide protective pipe scaffold in lieu of swing scaffold & welded wire mesh | 03/26/2021 | |
Amendment | $39,810.00 |
CO#3 75857 Change doors & hardware & add 3 door lights | 05/20/2021 | |
Amendment | $0.00 |
03/28/2023 | CO#4 76297 no cost time extension | 08/17/2021 |
Amendment | $966,571.00 |
CO # 5 75959 Additional labor and materials for window and ramp installation | 10/12/2021 | |
Amendment | $308,279.00 |
CO#6 76003 Increase funds to comply with specifications | 01/28/2022 | |
Amendment | $92,629.00 |
CO #8 76235 increase additional safety repairs | 03/25/2022 | |
Amendment | $36,238.00 |
CO#7 76032 Roof framing & slab repairs | 04/13/2022 | |
Amendment | $19,273.00 |
CO# 14 76832 Repair exterior facade | 06/22/2022 | |
Amendment | $445,157.00 |
CO# 9 76429 Removal of brick facade and steel beams repair | 06/30/2022 | |
Amendment | $83,971.00 |
CO#13 76830 Added work flashing & vents | 07/08/2022 | |
Amendment | $0.00 |
05/11/2023 | CO #12 77062 No cost time extension | 07/15/2022 |
Amendment | $32,545.00 |
CO #15 76923 Steel column reinforcement | 07/21/2022 | |
Amendment | $14,456.00 |
CO 16 77048 Steel reinforcement and stub column adjustment | 08/02/2022 | |
Amendment | $109,759.00 |
CO#10 76430 Reinforce existing beams | 08/15/2022 | |
Amendment | $70,774.00 |
CO#17 76808 North & east facing set back elevation flange & web reinforcement | 08/22/2022 | |
Amendment | $163,442.00 |
CO#21 76838 field conditions north elevation windows | 12/20/2022 | |
Amendment | $69,139.00 |
CO#18 77305 Roof slab repair | 12/30/2022 | |
Amendment | $132,004.00 |
CO#22 76813 steel lintel angles | 02/02/2023 | |
Amendment | $149,920.00 |
CO#19 76841 Masonry removal | 02/21/2023 | |
Amendment | ($37,097.00) |
CO#20 76287 Structural tubes and TE | 03/27/2023 | |
Amendment | $1,139,965.00 |
11/09/2023 | CO#24 77930 Additional steel support for watertable & time extension | 03/30/2023 |
Amendment | $0.00 |
10/28/2024 | CO #25 79381 No cost time extension | 11/15/2023 |