Vendor Name: HARRISON & BURROWES BRIDGE CONSTRUCTORS INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263826
Current Contract Amount: $29,535,303.45
Spending to Date: $29,535,303.45
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $26,855,268.55 |
02/15/2019 | 11/30/2020 | NY Rt 7 Bridge Rehabilitation & Pavement Repair Albany & Rensselaer Counties | 02/15/2019 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $175,786.20 |
CO#3 Overruns of Concrete Joint Panel Repairs | 08/01/2019 | |
Amendment | $13,009.60 |
CO#4 New Items Hudson River Bridge Rehab. | 09/10/2019 | |
Amendment | $87,964.39 |
CO#5 New Dry Swale Items | 09/23/2019 | |
Amendment | $51,767.93 |
CO#6 Overruns for Concrete Joint Panel Repairs & Top Items | 10/15/2019 | |
Amendment | $21,735.10 |
CO#8 New Items Hudson River Bridge Rehab. | 11/01/2019 | |
Amendment | $15,351.50 |
CO#9 Item increases and decreases | 11/19/2019 | |
Amendment | $50,241.13 |
CO#10 Increase to Items for Overruns | 12/17/2019 | |
Amendment | $106,611.65 |
CO#13 New Items | 04/22/2020 | |
Amendment | $7,797.86 |
CO#15 New Item & Additional Work | 07/10/2020 | |
Amendment | $5,715.05 |
CO#18 FAW Various Guide Rail & Check Dam Repairs | 07/30/2020 | |
Amendment | $8,400.60 |
CO#19 Renegotiated item for Removal of Structural Concrete & Replace with New Structural Concrete | 08/17/2020 | |
Amendment | ($985.62) |
CO#21 New Items Transition Rail to Concrete Barrier Repairs & Drainage | 09/04/2020 | |
Amendment | $15,792.13 |
CO#22 New Bearing Stiffeners for Ramp Abutments | 09/23/2020 | |
Amendment | $457,062.82 |
CO#23 New fencing & lighting items for bridges | 10/14/2020 | |
Amendment | $315,945.16 |
CO#24 Adding New Rail Joint & Pave Stripe Items | 11/06/2020 | |
Amendment | $0.00 |
06/30/2021 | CO#25 No Cost Time Extension | 11/19/2020 |
Amendment | $983,328.14 |
Change order #26 item increase and decreases | 01/27/2021 | |
Amendment | ($65,030.39) |
Change order #22 new bearing stiffeners for Ramp X & Y abutments | 02/17/2021 | |
Amendment | ($43,543.43) |
Change order #28 new concrete and ramp repair | 03/05/2021 | |
Amendment | $595,492.27 |
CO#30 item increases and decreases | 07/14/2021 | |
Amendment | ($183,020.06) |
CO #31 Cleanup | 12/08/2021 | |
Amendment | $2,023.31 |
CO#32 Required funding fix | 02/02/2022 |