Vendor Name: YONKERS CONTRACTING CO INC
Authority Name: Thruway Authority
Department/Facility Name: New York State Thruway Authority
Contract Number: D214583
Current Contract Amount: $46,005,375.70
Spending to Date: $1,045,558.49
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $39,311,727.80 |
07/18/2018 | 12/21/2019 | Shared Path Facilities & Bicycle/Pedestrian Connection New NY Bridge MP 16-75 Rockland Co TANY18-12 | 07/18/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $195,000.00 |
CO#1 Shared Use Path Safe Opening | 09/18/2019 | |
Amendment | ($4.28) |
CO#2 New & Decreased Item Unclassified Excavation & Disposal | 01/07/2020 | |
Amendment | $0.00 |
06/25/2020 | CO#3 NCTE | 02/19/2020 |
Amendment | $0.00 |
04/03/2020 | CO#3 Correction to NCTE Seq 18 | 02/27/2020 |
Amendment | ($2,992.91) |
Change order #3 decrease in quantities and increase for traffic signals change | 04/06/2020 | |
Amendment | ($3,337.75) |
CO#4 New Items Chg lighting system &traffic signal system to have separate service per DOT requiremt | 06/16/2020 | |
Amendment | ($755.38) |
CO#5 New Item Watermain Relocations & Connections & Decreases to Steel Coating Mulch Seed | 06/17/2020 | |
Amendment | $0.00 |
07/20/2020 | CO#6 NCTE | 07/10/2020 |
Amendment | $151,000.00 |
CO#7 Force Estimate for Relocating Fiber Optic Line & Work at Swale along Exit 10 Ramp I-87 NB | 10/23/2020 | |
Amendment | $131,500.00 |
CO#8 Estimate for Winter Production for Safe Opening of Shared Use Path | 10/23/2020 | |
Amendment | $159,483.43 |
CO#9 Estimate Resurface Steel & Power Washing Abutment & Pier | 10/26/2020 | |
Amendment | $140,351.25 |
CO#10 Increase for 5 New Items Rework Grade Changes Rebar Couplers Flagging Bridge Rail Modification | 10/26/2020 | |
Amendment | $0.00 |
10/30/2020 | CO#11 No cost time extension | 11/13/2020 |
Amendment | $142,314.68 |
Change order #11 additional earthwork and trail improvements | 12/29/2020 | |
Amendment | ($0.03) |
CO#12 Item in creases and decreases. | 12/31/2020 | |
Amendment | $230,084.43 |
Change order #13 new items | 01/04/2021 | |
Amendment | $262,896.40 |
Change order #14 new items | 01/04/2021 | |
Amendment | $261,554.41 |
Change order #15 new items | 02/24/2021 | |
Amendment | $290,286.84 |
Change order #16 new items | 02/24/2021 | |
Amendment | ($476.10) |
CO#17 Decreases to items not fully utilized & increases for added work locations | 03/17/2021 | |
Amendment | $726,860.30 |
Change order #18 additional survey costs | 05/04/2021 | |
Amendment | $280,603.40 |
Change order #19 bicycle/pedestrian path | 05/26/2021 | |
Amendment | $307,131.74 |
Change order #20 bicycle/pedestrian path | 05/26/2021 | |
Amendment | $136,150.35 |
CO#21 New items electrical work & dog park | 06/17/2021 | |
Amendment | $1,022,788.13 |
CO#22 New & changed items bicycle/pedestrian path | 08/30/2021 | |
Amendment | $1,698,229.00 |
CO#23 FAW extended overhead costs | 12/28/2021 | |
Amendment | $570,802.43 |
CO#24 New items winter protection & engineering costs | 12/28/2021 | |
Amendment | ($5.72) |
CO#25 Reconciliation of field change order item | 03/07/2022 | |
Amendment | ($5,816.72) |
CO#26 New item fuel price adjustment | 03/29/2022 |