Vendor Name: D A COLLINS CONSTRUCTION CO INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263577
Current Contract Amount: $11,762,018.02
Spending to Date: $11,762,018.02
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $9,745,743.62 |
03/27/2018 | 12/15/2019 | Bridge rehab, Rts 9/20, CSX/Amtrak RR and RT9/20 over 9J Amtrak RR; Rensselaer County | 03/27/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $650,000.00 |
CO#1 Increase in Amtrack FAW Services | 06/22/2018 | |
Amendment | $2,012.68 |
CO#2 New/Inc/Decrease Items Bridge Rehabilitation Amtrak RR Rensselaer County | 10/29/2018 | |
Amendment | $56,840.86 |
CO#4 New Item Bridge Rehab Route 9&20 Over Amtrak RR Rensselaer County | 12/05/2018 | |
Amendment | $171,010.26 |
CO#5 New Remove & Install Angles Item | 12/20/2018 | |
Amendment | $5,615.28 |
CO#7 Add New FA Item | 03/04/2019 | |
Amendment | $146,037.05 |
CO#9 Additional Disposal of Hazardous Paint Waste Containing Lead | 04/12/2019 | |
Amendment | $165,553.92 |
CO#10 New Item Stage 1 Thermal Deck Heating | 04/30/2019 | |
Amendment | $220,380.70 |
CO#13 Temporary Closure Pours | 05/21/2019 | |
Amendment | $17,011.49 |
CO#15 New Item Rehab Of Two Bridges Route 9&20 Rensselaer County | 06/12/2019 | |
Amendment | $10,843.58 |
CO#17 Add New Items for Sidewalk Regrading & Asphalt Removal | 07/12/2019 | |
Amendment | $50,468.79 |
CO#14 Substructure Winter Concrete Pedestals | 08/06/2019 | |
Amendment | $3,334.24 |
CO#18 New Bridge Bearing Shim Plates Item | 09/05/2019 | |
Amendment | $60,161.44 |
CO#21 New Items & Extra Work Bridge Rehabilitation | 09/20/2019 | |
Amendment | $30,294.65 |
CO#22 New Items Bridge Rehabilitation | 10/04/2019 | |
Amendment | $118,537.12 |
CO#25 Type C Repairs & Steel Angles Bridge 1 Stage 3 | 10/28/2019 | |
Amendment | $237,271.32 |
CO#26 Miscellaneous Overruns | 11/14/2019 | |
Amendment | $12,677.01 |
CO#28 New item | 12/11/2019 | |
Amendment | $7,491.38 |
CO#19 New Item Concrete Barrier Removal Traffic Control | 02/05/2020 | |
Amendment | $149,715.87 |
CO#27 Added Work to Remove & Install New Angles & Steel Web Fill Plate Repairs | 03/12/2020 | |
Amendment | $3,883.99 |
"FAW" New Item #950.09 Drainag | 03/26/2020 | |
Amendment | $18,519.80 |
CO#30 Engineering Costs | 04/13/2020 | |
Amendment | $8,392.81 |
CO#31 New Item Second Season Traffic Control/Truck Detour | 05/04/2020 | |
Amendment | $6,337.18 |
CO#32 New Force Account Item Buried Removal Of Concrete Wall | 05/26/2020 | |
Amendment | $37,043.25 |
CO#33 Existing Item Overruns & Cleanup | 07/20/2020 | |
Amendment | $133,254.63 |
CO#34 Extra Work Second Season Bridge Work | 09/25/2020 | |
Amendment | ($227,351.24) |
CO# 36 Cleanup CO | 03/30/2022 |