Vendor Name: LANCASTER DEVELOPMENT & TULLY CONSTRUCTION CO LLC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263788
Current Contract Amount: $33,264,420.75
Spending to Date: $33,264,420.75
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $31,077,048.27 |
11/29/2018 | 12/11/2019 | I-87 Exit 4 Access Improvement Albany County | 11/30/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $26,652.99 |
01/17/2020 | CO#1 New ITS Items | 03/01/2019 |
Amendment | $986,300.00 |
CO#5 New Earthwork Items | 05/16/2019 | |
Amendment | ($51,288.75) |
CO#7 Item increases and decreases | 07/03/2019 | |
Amendment | $26,688.75 |
CO#8 New item and item decrease | 07/16/2019 | |
Amendment | $18,210.00 |
CO#9 New Item I-87 Exit 4 Access Improvement Albany County | 07/30/2019 | |
Amendment | $52,287.60 |
CO#10 New Item I-87 Access Improvements | 08/06/2019 | |
Amendment | $12,687.95 |
CO#11 New item | 08/19/2019 | |
Amendment | $9,563.26 |
CO#12 New FAW Drainage Item | 09/17/2019 | |
Amendment | $27,124.04 |
CO#13 New Items Exit 4 Access Improvements | 10/02/2019 | |
Amendment | $7,653.92 |
CO#14 Reset Drainage | 10/23/2019 | |
Amendment | $6,751.50 |
CO#16 New Item Access Improvements | 11/01/2019 | |
Amendment | $5,067.90 |
CO#17 New FAW Drainage Item | 11/25/2019 | |
Amendment | $292,800.00 |
CO#20 Additional True & Leveling FS Superpave HMA 80 Series | 12/16/2019 | |
Amendment | $493,610.47 |
CO#23 Drilled Shaft For Overhead Sign Structures Renegotiated | 12/31/2019 | |
Amendment | ($2,516.54) |
CO#24 Decreases & New FAW Utilities Item | 02/10/2020 | |
Amendment | $0.00 |
06/01/2020 | CO#27 Item adjustment and time extension | 02/19/2020 |
Amendment | ($2,641.80) |
CO#27 Unclassified Excavation & Disposal & New Items | 03/26/2020 | |
Amendment | $527,477.03 |
CO#28 New Earthwork Incidental Construction Drainage Utility Items & Item Increases & Decreases | 04/29/2020 | |
Amendment | $475,496.82 |
CO#32 overruns & FAW extra work | 06/01/2020 | |
Amendment | $97,973.16 |
CO#33 New Item Drainage Eliminated Materials | 06/15/2020 | |
Amendment | ($58,047.64) |
Change order #34 increase/decrease items & added items | 02/23/2021 | |
Amendment | ($292,013.69) |
Change order #36 increased box beams and topsoil | 03/05/2021 | |
Amendment | ($45,712.26) |
Change order #37 decreased earthwork | 03/12/2021 | |
Amendment | ($426,752.23) |
CO#38 Final | 10/06/2021 |